Every week someone calls with a number from a builder website and a lot they found online. The number is almost always the building alone. That is fine, as long as you know what sits around it.
The building
This is the plan price at a finish level: frame, steel, slab, and whatever finishes that level includes. It is the biggest line, and the easiest to compare between builders.
The site
Site work is where budgets break. A cleared lot with city water and power at the road might add $25,000. A wooded lot that needs a well, an aerobic septic system and 800 feet of new power line can add $100,000 or more. Same house, very different total.
Before you make an offer on land, find out three things: how far the nearest power pole is, whether neighbors are on wells, and what the soil looks like for septic. Your co-op, a well driller and a soil test will tell you most of it.
The soft costs
Survey, foundation engineering, septic design and permits usually run $4,000 to $12,000. Then set aside 5 to 10 percent of the build as contingency. You probably will not spend it all. You will be glad it was there.
Put it together
Our Plan your build tool adds all of this for your ZIP and your answers. It is not a quote, but it is the right number to take to a lender.
Quick answers.
How much does site work add to a barndominium?
How much contingency should I plan for?
Run your own numbers
See the all-in price for your land.
Pick a plan, answer six questions about the site and get a range you can take to a lender.
Plan your build